No
|
Project
|
Package
|
Invitation notice number
|
Procurement Method
|
Name of the winning bidder
|
1
|
Noi Bai – Lao Cai Highway Project
|
Package B2: Suplly and Delovery of Operations and Maintenance Equipment
|
Bidding Newspaper No.214 dated 25 October 2013
Bidding Newspaper No.215 dated 28 October 2013
Bidding Newspaper No.216 dated 29 October 2013
|
International Competitive Bidding (ICB), 01 envelope
|
Hiep Hoa Equipment of Environmental & Trading Co., Ltd
|
- Contract Price: 32 billions VND
- Amount of the contract awarded: 24,481,082,727 VND
- Approval decision: No. 440/QD-VEC-HDTV dated 09 July 2014 signed by VEC’s Chairman
- Type of Contract: Lump sum
- Contract implementation time: 150 days